Power Plant Engineers Ltd v Business Partner International [2019] KEELC 2732 (KLR)

[2019] KEELC 2732 (KLR) Environment & Land Court
Read PDF
Court
Environment & Land Court
Case number
2732
Citation
[2019] KEELC 2732 (KLR)
Decided
27 June 2019
Beta Machine-generated summary. Automatically produced by AI from the judgment text — it may be incomplete or inaccurate. Always verify against the full judgment below. Not legal advice.

Summary at a glance

TypeApplication for Leave to File Defence Out of TimePostureApplication dismissedCoramHarris
Application dismissed

Facts

The plaintiff failed to file its defence within the prescribed time, claiming an inadvertent omission in the handover report by the advocate. The defendant argued that the application was res judicata due to a similar application previously refused.

Issues

  • Whether the plaintiff should be granted leave to file its defence out of time
  • Whether the application is res judicata

Reasoning

The court found the plaintiff's explanation for the delay to be insufficient and not a fit case to exercise its discretion in favor of the plaintiff.

Outcome

Application dismissed

Orders

  • The application was dismissed with reasons given