Stephen Ombaki Momanyi v Bedrock Holdings Limited [2019] KEELRC 369 (KLR)
- Court
- Employment & Labour Relations Court
- Case number
- 369
- Citation
- [2019] KEELRC 369 (KLR)
- Decided
- 24 October 2019
Summary at a glance
TypeLabour DisputePostureClaimant's case against Respondent for unpaid wages, notice pay, severance pay, and other benefitsCoramM. MBAR?
Claimant is awarded Ksh.7,500 for 20 days worked in September 2016, Ksh.96,866 in underpayments, Ksh.24,170.70 in rest days pay, Ksh.5,665 in service pay, and a certificate of service.
Facts
Claimant was employed by Respondent as a night guard from March 19, 2015 to September 20, 2016. He was not provided with a contract of service and was not issued with a payment statement. He was not paid for work in September 2016 and was declared redundant.
Issues
- Employment status
- Unpaid wages
- Notice pay
- Severance pay
- Rest days pay
- Public holidays pay
Reasoning
Claimant was employed by Respondent and was entitled to wages and benefits as per the Wage Orders. The termination of employment was fair and notice was given. The claimant was not paid for work in September 2016 and was entitled to severance pay.
Outcome
Claimant wins
Orders
- Pay for 20 days worked in September, 2016
- Underpayments awarded
- Rest days' pay
- Service pay
- Certificate of service
Remedies
- Payment of wages and benefits
- Certificate of service