Congress Rental South Africa v Kenyatta International Convention Centre [2016] KEHC 1153 (KLR)

[2016] KEHC 1153 (KLR) High Court of Kenya
Read PDF
Court
High Court of Kenya
Case number
1153
Citation
[2016] KEHC 1153 (KLR)
Decided
10 November 2016
AI Summary Beta Machine-generated — may contain errors. Not legal advice.
TypeArbitration DisputePostureAppeal from a decision to dismiss an application for interim measures and to award costsCoramF. TUIYOTT
Holding

The dispute is subject to arbitration and the Plaintiff's application for interim measures is dismissed. The Plaintiff is ordered to pay the Defendant's costs.

Facts

The Plaintiff sought an interim injunction and damages for breach of contract, while the Defendant sought to refer the matter to arbitration.

Issues

  1. Whether the dispute is subject to arbitration
  2. Whether the Plaintiff's application for interim measures was properly brought

Reasoning

The Court accepted that the dispute is subject to arbitration and that the Plaintiff's application for interim measures was not properly brought, as it proceeded on the basis that the Arbitration clause did not apply.

Outcome

Appeal dismissed

Orders

  • The Plaintiff's application for interim measures is dismissed
  • The Plaintiff is ordered to pay the Defendant's costs

Remedies

  • Costs to the Defendant

Authorities cited

Legislation (1)
  • Civil Procedure Act
Experimental AI summary generated by a language model, not a lawyer. It may contain errors or omissions and must not be relied on for legal decisions — the full judgment below is the authoritative source.
Full judgment 0.1 MB · PDF

Loading judgment…

Cite this case


        
        
      

Share this case