Elecage Holdings Limited v Comarco Construction Company Limited [2016] KEHC 8562 (KLR)

[2016] KEHC 8562 (KLR) High Court of Kenya
Read PDF
Court
High Court of Kenya
Case number
8562
Citation
[2016] KEHC 8562 (KLR)
Decided
6 April 2016
AI Summary Beta Machine-generated — may contain errors. Not legal advice.
TypeCivil SuitPostureSummary Judgment ApplicationCoramFRED A. OCHIENG
Holding

The court finds the defendant owed Kshs. 24,100,000 to the plaintiff as of November 5, 2015, and orders payment of this sum with interest at 14% per annum from November 28, 2014, and costs of the suit and application.

Facts

The plaintiff, Elecage Holdings Limited, claimed Kshs. 36,100,000 and costs from the defendant, Comarco Construction Company Limited, for unpaid balance after the defendant had already paid Kshs. 13,000,000.

Issues

  1. Defendant's liability for the balance due
  2. Interest and costs

Reasoning

The defendant did not file a defence and made payments, confirming no defence to the claims. The court entered judgment in favor of the plaintiff for the balance due.

Outcome

Judgment in favor of the plaintiff for Kshs. 24,100,000 with interest and costs.

Orders

  • Payment of Kshs. 24,100,000 to the plaintiff
  • Interest on the sum at 14% per annum from November 28, 2014
  • Payment of costs of the suit and application

Remedies

  • Payment of Kshs. 24,100,000
  • Interest on the sum
  • Payment of costs